Site visit to check site access issues at very early stage of project 16th June 2008
Steelwork well underway despite weather! 7th July 2008
Progress visit prior to the scheduled delivery. Steelwork nearing completion 17th July 2008
Steelwork complete, delivery to proceed on schedule
23rd July 2008
Installation begins - Day 1 of 6 24th July 2008
Good progress being made 24th July 2008
Installation - Day 2 of 6 everything on schedule 25th July 2008
Day 4 of 6 everything still on track
29th July 2008
An area completed, ready for grouting 29th July 2008