Preliminary site visit to check access issues 16th June 2008
Second visit a month later, to ensure progress is on schedule 17th July 2008
Steel frame installation ahead of schedule 23rd July 2008
Steel frame on second block being erected 29th July 2008
Steel frame progressing well 30th July 2008
Final inspection of site prior to first phase of the floor installation 30th July 2008